Re: Freeze date?
On Wed, Sep 07, 2016 at 02:02:13PM +0200, Onsemeliot wrote:
> On Wed, 2016-09-07 at 11:48 +0000, Gianfranco Costamagna wrote:
> > https://release.debian.org/
> >
> > [2016-Nov-05] Transition freeze
> > [2016-Dec-05] Mandatory 10-day migrations
> > [2017-Jan-05] Soft freeze (no new packages, no re-entry, 10-day migrations)
> > [2017-Feb-05] Full freeze
>
> Than you, Gianfranco. This is exactly what I was hoping for.
Just note that the full-freeze date means "your package has to have migrated to testing",
so it is effectifly Feb 05 minus 10 days. Many people were bitten by this when Jessie
was frozen.
> Best,
> Onsemeliot
>
--
tobi