On Sun, Sep 26, 2004 at 06:17:44AM +0200, Joey Hess wrote: > Here is the timeline we developed at the meeting yesterday, covering all > of next month and two releases of d-i, a minor release to get users to test > the current installer (name undecided, temporarily called "tc2"), and rc2. > > Note that there are currently only 3 days until the last udeb changes for > tc2, and that there are only 4 days to make string changes before the > string freeze. It would be really nice if someone could upload a new version of discover1 with the changes I made during the oldenburg meeting. I'm quite confident they are ok. They were successfully tested on powerpc (new and oldworld) and on some other arch I don't remember by joshk. They only lack testing on i386. All the changes are in cvs repo on alioth. Thanks for sponsoring this Gaudenz