Here is the timeline we developed at the meeting yesterday, covering all
of next month and two releases of d-i, a minor release to get users to test
the current installer (name undecided, temporarily called "tc2"), and rc2.
Note that there are currently only 3 days until the last udeb changes for
tc2, and that there are only 4 days to make string changes before the
string freeze.
29 Sep last day for udeb changes for tc2
udebs propigated to testing (rc1 breaks)
30 Sep release tc2 (or give up on the idea)
string freeze begins
start building full CDs for tc2
4 Oct full CDs finish building for tc2, are released
7 Oct translation uploads
last day to upload fixes to packages on initrds
8 Oct initrd builds start for rc2
21 Oct initrd builds finish (or earlier..)
last day for uploads of any udebs or debs for rc2
22 Oct udebs propigated to testing (tc1 breaks)
full debian freeze probably starts here
final netinst and businesscard CD builds
begin full CD builds
23 Oct testing begins
26 Oct full CD builds finish
29 Oct web site updates
and rc2 release
--
see shy jo