Dear colleagues,The Release Team would like to propose a bookworm freeze timeline. Don't worry, the timeline is a plan, if serious (timing) issues come up we will adapt. However, before making the plan public in a wider audience, we'd like to know from you if you already foresee clashes in timing from the kernel, gcc, binutils and glibc that we should take into account. Does the following timeline seem reasonable to you considering plans of your upstream?
(the bullseye schedule + 2 years): 2023-01-12 - Milestone 1 - Transition and Toolchain freeze 2023-02-12 - Milestone 2 - Soft Freeze 2023-03-12 - Milestone 3 - Hard Freeze TBA - Milestone 4 - Full Freeze On behalf of the Release Team, Paul