Re: Planning for next squeeze point release (6.0.4)



On Mon, Dec 12, 2011 at 11:07:32PM +0000, Adam Barratt wrote:
>Hi,
>
>Yep, it's that time again.  Based on a bi-monthly schedule, 6.0.4 would
>be due around mid-January.
>
>We may want to adjust timings a little, so that we don't end up trying
>to set deadlines for things like kernel and d-i changes being ready over
>the holiday period.
>
>As an opening gambit, I'd propose we look at one of the following
>Saturdays in January: 14th, 21st, 28th.

At this point, any of those should work for me.

-- 
Steve McIntyre, Cambridge, UK.                                steve@einval.com
"Further comment on how I feel about IBM will appear once I've worked out
 whether they're being malicious or incompetent. Capital letters are forecast."
 Matthew Garrett, http://www.livejournal.com/users/mjg59/30675.html