Re: release update: d-i schedule, release notes, deep freeze



On Tue, Mar 13, 2007 at 11:23:52PM +0100, Luk Claes wrote:
> N-14 = 19 Mar 2007:
> 
> 	20 RC bugs.  D-I RC2 releases.  Users are encouraged to use the
> 	debian-installer for new installs and to begin upgrading systems
> 	from sarge to the security-supported etch, and report any
> 	problems found.
> 
> N-7  = 26 Mar 2007:
> 
> 	~0 RC bugs.  Final adjustments to packages in response to
> 	install and upgrade feedback.  Finalization of the release
> 	notes.
> 
> N    =  2 Apr 2007:
> 	0 RC bugs.  Barring any problems that would cause us to need to
> 	re-roll the installer <knock on wood>, we should be ready to
> 	release.

As far as upgrade are concerned, this is unrealistic. If users start
upgrading systems on 19 Mar 2007, we will not get significant feedback
before two weeks after that date, at which point the schedule plan for
the release to have already happen.

Cheers,
-- 
Bill. <ballombe@debian.org>