Re: Point release schedule



On Mon, Sep 05, 2011 at 10:28:25AM +0200, Daniel Baumann wrote:
> On 09/04/2011 06:14 PM, Philipp Kern wrote:
> >so apparently September is a very bad month to get CDs done.  I'm hereby
> >proposing the following with the hope that we can do it that way:
> >
> >  * Lenny: October 1st
> >  * Squeeze: October 8th
> 
> you forgot, once again, to cc d-live@l.d.o.
> 
> >Can we do that, pretty please?  :)
> 
> works for mee too.

FSVO "forgot".  I am following [0].

That said, we saw that discussed on #d-live for the 6.0.1 point release and you
basically said that point releases are a no brainer and started only once the
mirrors are updated.  Furthermore you said this is usually on the next day
anyway.

The notification about when the point release really is, is something we surely
send you.  The thing is that it's already hard to get the three teams together
as-is, and I don't want to add a fourth.  But please don't take this as an
offence, it's purely something whose scheduling gets massively harder if you
add another team that has mainly one guy that triggers the build (c.f. CD).

Kind regards,
Philipp Kern

[0] http://wiki.debian.org/Teams/ReleaseTeam/PointReleaseCheckList
-- 
 .''`.  Philipp Kern                        Debian Developer
: :' :  http://philkern.de                         Stable Release Manager
`. `'   xmpp:phil@0x539.de                         Wanna-Build Admin
  `-    finger pkern/key@db.debian.org

Attachment: signature.asc
Description: Digital signature


Reply to: