Re: slink is gone, goals for potato?
> General project goals:
> potato estimated release - between June and August 1999
Seems very reasonable if we freeze potato in 4-6 weeks.
> Filesystem Hierarchy Standard (FHS)
> Changes needed, off the top of my head -
> * move /usr/doc/* to /usr/share/doc/*
> ...
This, together with the libc, kernel and Perl upgrades should take a
good two months to debug.
I would suggest that if we aim for these three things initially
implemented within the next 4-6 weeks, and then freeze, we will have
more than enough work to do to debug all of the non-compliant broken
code.
Julian
=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-