Re: Scheduling the 7.5 point release



On 04/21/2014 19:35, Adam D. Barratt wrote:
> On Tue, 2014-03-18 at 23:03 +0000, Adam D. Barratt wrote:
>> On Sat, 2014-03-15 at 09:01 +0000, Adam D. Barratt wrote:
>>> On Sat, 2014-03-01 at 21:44 +0100, Niels Thykier wrote:
>>>> We are slowly starting to prepare for the 7.5 point release and are
>>>> suggesting one of the four following weekends:
>>
>> Based on the replies and looking again at a calendar, let's go for:
>>
>>>>  * April 26th/27th
> 
> Given a regression in the latest kernel upload in p-u (#745137) and a
> lack of feedback so far on one of the larger hardware backports included
> therein (igb), I'm wondering if it might make sense to push the date
> back a week, to May 3rd, and give ourselves time to get things sorted
> without rushing at the end of the week.
> 
> On the initial call, everyone indicated that they would be available
> that weekend; is that still the case?

Should still be okay.