Re: Scheduling the 7.5 point release



On Mon, Apr 21, 2014 at 06:35:59PM +0100, Adam Barratt wrote:
>On Tue, 2014-03-18 at 23:03 +0000, Adam D. Barratt wrote:
>> On Sat, 2014-03-15 at 09:01 +0000, Adam D. Barratt wrote:
>> > On Sat, 2014-03-01 at 21:44 +0100, Niels Thykier wrote:
>> > > We are slowly starting to prepare for the 7.5 point release and are
>> > > suggesting one of the four following weekends:
>> 
>> Based on the replies and looking again at a calendar, let's go for:
>> 
>> > >  * April 26th/27th
>
>Given a regression in the latest kernel upload in p-u (#745137) and a
>lack of feedback so far on one of the larger hardware backports included
>therein (igb), I'm wondering if it might make sense to push the date
>back a week, to May 3rd, and give ourselves time to get things sorted
>without rushing at the end of the week.
>
>On the initial call, everyone indicated that they would be available
>that weekend; is that still the case?

Still works for me, yep.

-- 
Steve McIntyre, Cambridge, UK.                                steve@einval.com
"Further comment on how I feel about IBM will appear once I've worked out
 whether they're being malicious or incompetent. Capital letters are forecast."
 Matthew Garrett, http://www.livejournal.com/users/mjg59/30675.html