Re: Re-planning for 12.6
On Sun, Apr 21, 2024 at 05:44:48PM +0100, Andy Simpkins wrote:
>
> On 21/04/2024 01:57, Steve McIntyre wrote:
> > On Sat, Apr 20, 2024 at 05:41:13PM +0100, Jonathan Wiltshire wrote:
> > > On Thu, Apr 18, 2024 at 10:58:41PM +0100, Steve McIntyre wrote:
> > > > Hiya!
> > > >
> > > > Not wanting to pester *too* much, but where are we up to?
> > > >
> > > Right now I can still have 27th April on the cards but we're missing FTP and
> > > press. It's next week, we'd have to know this weekend and get frozen.
> > > Mark indicated "maybe" and no answer from press.
> > >
> > > If that date works please reply urgently otherwise we're looking into May
> > > and possibly just skipping to line up with the final bullseye anyway.
> > It works for me, I guess. Dunno about other folks.
> >
>
> I can still do 27th but as I have already stated Isy is now unavailable
> until July due to exams.
>
> Please can we make a decision by Tuesday otherwise I'll end up doing
> something else....
Too late now in any case. SRMs will regroup and decide whether we push for
one in May or just wait for June anyway.
--
Jonathan Wiltshire jmw@debian.org
Debian Developer http://people.debian.org/~jmw
4096R: 0xD3524C51 / 0A55 B7C5 1223 3942 86EC 74C3 5394 479D D352 4C51
ed25519/0x196418AAEB74C8A1: CA619D65A72A7BADFC96D280196418AAEB74C8A1
Reply to: