Re: Planning for final lenny point release (5.0.10)



On Tue, 2011-12-13 at 21:39 +0100, Joerg Jaspert wrote:
> On 12693 March 1977, Adam D. Barratt wrote:
> 
> > From the experience of etch's EOL point release, we'll need a little
> > time to sort out any remaining build issues for security packages after
> > the end of support.  The earliest we'd therefore be looking at would be
> > the weekend of 11/12th February.
> 
> Does sound fine to me, but do you really want only one week between the
> end of security and the final point release? Its not much time, should
> security really push out something that ends up plenty broken... How
> high THAT possibility is i dont know, but meh.

It was an absolute earliest date but, yes, we should probably leave a
little longer just in case[tm].

To be on the safe side, maybe we should consider weekends between mid
February and mid-to-late March?

Cheers,

Adam