On Thursday 27 July 2006 14:13, Goswin von Brederlow wrote:
> And the planed date for that is?

From "bits from the release team", 02/05/06 22:36:
N-45   = Wed 18 Oct 06: general freeze [about 2 months after base
                        freeze, d-i RC]
N      = Mon  4 Dec 06: release [1.5 months for the general freeze]

> Will that build be done from etch, meaning apt has to be in etch at
> that point?

d-i builds are done in unstable, just like builds for any other package; 
of course, we should make sure that any packages that d-i uses during 
that build end up in Etch before the release