Re: Scheduling the 7.5 point release



On Tue, 2014-03-18 at 23:03 +0000, Adam D. Barratt wrote:
> On Sat, 2014-03-15 at 09:01 +0000, Adam D. Barratt wrote:
> > On Sat, 2014-03-01 at 21:44 +0100, Niels Thykier wrote:
> > > We are slowly starting to prepare for the 7.5 point release and are
> > > suggesting one of the four following weekends:
> 
> Based on the replies and looking again at a calendar, let's go for:
> 
> > >  * April 26th/27th

Given a regression in the latest kernel upload in p-u (#745137) and a
lack of feedback so far on one of the larger hardware backports included
therein (igb), I'm wondering if it might make sense to push the date
back a week, to May 3rd, and give ourselves time to get things sorted
without rushing at the end of the week.

On the initial call, everyone indicated that they would be available
that weekend; is that still the case?

Cheers,