Quoting Cyril Brulebois (kibi@debian.org): > The deadline should be pretty clear, and should let time for doc / > translation updates, especially on the installation guide front. > Christian, could you perform your l10n coordination magic bits? I'll send yet another call for updates, but I don't expect much updates now. I made so much noise for beta1 that nearly all languages teams coped and we have a stunning number of fully complete translations (even for some very rarely used D-I packages). > > Dates would be: > 2012/08/25-26: development ends this week-end. > 2012/09/01-02: d-i wheezy beta 2 is released. > > Hopefully there won't be too many changes in such a timeframe, so the > one week for coordinating with release team, ftmasters, and cd team > should be sufficient. I commit myself to help out as much as possible in achieving this. I'm currently going through all D-I packages that have pending changes in GIT and will upload them. The goal is to avoid staging stuff.