[Date Prev][Date Next] [Thread Prev][Thread Next] [Date Index] [Thread Index]

Re: release status



On Wed, Mar 03, 2004 at 04:36:16PM -0500, Joey Hess wrote:
> We're still on track for release on the 15th. Here's a schedule up to
> then:
> 
> March 3rd       No changes to libraries past this point.
> March 6th       Final code changes for i386 enter the archive.
>                       (except new udebs and possibly partman)
> March 7th       All udebs to be copied from unstable to testing.
>                 First possibly final i386 CDs built; testing.
>                 String freeze begins.
> March 10th      String feeeze ends.
> March 14th      Final changes to udebs in archive.
>                 Final image and CD builds.
> March 15th	Release.
> 
> So we will be trying to get i386 into a releasable state by weekend, and
> after that concentrate on making sure the other architectures are ready.
> Here, again is a checklist for what needs to be done for an architecture
> before release:
> 
>  1. CD images builds should be working (if applicable)
>  2. images must be in debian archive
>  3. at least one successful installation report per boot method
> 
> Here is a short list of things that need to be done still before release:
> 
>  - fix all beta2 errata (a must)
>         - reiserfsprogs not installed

Can #229328 be addressed? I've submitted a patch. It would greatly improve
LVM support in the installation process, as it's rather broken at present.

Andrew

Attachment: signature.asc
Description: Digital signature


Reply to: