Re: First draft of ROCm 6.1 Release Plan



On 2024-08-20 23:11, Christian Kastner wrote:
> I've created the first draft version of the release plan for 6.1 [1].

I just realized: assuming that the freeze for trixie will be sometime
around February or March, we have about ~6 months to get everything
finalized.

That sounds like a lot, but it isn't, considering that we have a number
of transitions to take care of. For bookworm, the transition freeze was
on January 12th.

We should really, /really/ aim to have
  * ROCm on at least 6.1 across the board
  * full support for Navi 3x and MI300
  * ROCm support in PyTorch and Blender.

Best,
Christian

> [1]: https://salsa.debian.org/rocm-team/community/team-project/-/wikis/ROCm-6.1-Release-Plan