On 2024-08-20 23:11, Christian Kastner wrote:
> I've created the first draft version of the release plan for 6.1 [1].
I just realized: assuming that the freeze for trixie will be sometime
around February or March, we have about ~6 months to get everything
finalized.
That sounds like a lot, but it isn't, considering that we have a number
of transitions to take care of. For bookworm, the transition freeze was
on January 12th.
We should really, /really/ aim to have
* ROCm on at least 6.1 across the board
* full support for Navi 3x and MI300
* ROCm support in PyTorch and Blender.
Best,
Christian
> [1]: https://salsa.debian.org/rocm-team/community/team-project/-/wikis/ROCm-6.1-Release-Plan