Re: Building linux (3h 44m, vs93)
On 03/09/2016 10:53 AM, Christian T. Steigies wrote:
> I remember the old days where the buildd would receive an email when a
> package was outdated. I don't think I received one, but maybe my local email
> forwarding is not set up properly.
Hmm. We should ask Aurelien about that. Maybe the notification mechanism
has changed.
> How long does building linux take nowadays, one week? Two? Maybe I should
> stop it, your shiny virtual machine will probably be finished before the
> real 68060...
Should take no longer than 7 hours according to statistics [1].
Adrian
> [1] https://buildd.debian.org/status/logs.php?pkg=linux&arch=m68k
--